NUK York
RES has completed a number of smaller projects at this site, to include a new platform installation, and jacketed pipe work fabrication and installation, the pipework being fabricated in our workshop and transported to, and installed and connected on site.
​
The system was pressure tested, certificate issued and all completed documentation.
​
This being a high hygiene site, requiring additional measures to protect the product, all works completed without issue and on time with good feedback on our performance.
​
All works completed between November 2019 and March 2020 with a value of £75000.
​
All installation requiring passivating and swab testing due to the nature of the site.
​
A dedicated site team meant consistency for the client project team, and site knowledge.